Fifty patents, nine targets, three 5G domains, and one week
A top intellectual property (IP) litigation firm faced a hard pre-trial deadline on a 5G patent case spanning 50 patents, nine accused targets, and three technology domains. Every chart was delivered on schedule.
Case study · Litigation support · Claim charts · Wireless / 5G
The situation
- Client
- A top IP litigation firm
- Matter type
- Patent infringement litigation
- Technology
- Wireless / 5G (three domains)
- Scope
- 50 patents, 9 accused targets
A partner at a top IP litigation firm came to GHB Intellect with a problem that is easy to describe and hard to solve: 50 patents, nine accused targets, three distinct 5G technology domains, and a pre-trial filing deadline one week out. The claim charts didn’t exist yet. They needed to.
The matter covered 5G base stations, carrier networks, and handsets, which call for different domain expertise. A wireless expert qualified in one area of the 5G specification isn’t interchangeable with one qualified in another. Finding the right people, coordinating several workstreams, and delivering litigation-ready charts under a single deadline takes project management as much as expertise.
The client had worked with GHB Intellect before. They called because they knew what the engagement required.
The challenge
- Primary constraint
- A 7-day hard deadline
- Complexity
- Three distinct 5G technology domains
- Targets
- Nine accused parties across carriers, equipment vendors, and device suppliers
Volume alone wasn’t the problem. Volume in a single domain, with a single pool of qualified experts, is a scheduling and workflow problem, and we handle it routinely. This matter was harder because 5G radio access network, 5G Core, and 5G handsets aren’t the same technical territory. Staffing them as if they were would have produced charts that couldn’t survive scrutiny.
The plan had to build three teams at once, one per domain, each able to deliver inside a seven-day window, with patents assigned by domain and a review workflow to catch technical errors before anything reached counsel.
A gap in a claim chart isn’t a minor editorial problem at trial. Every chart had to be technically accurate, claim-complete, and ready for deposition scrutiny, and the deadline left no room to redo work.
What GHB Intellect did
- Services deployed
- Claim chart development, team building by domain, project management
- Experts engaged
- Domain-matched practitioners across three subspecialties
- Delivery method
- Rolling batches with quality assurance (QA) gates
- Project management
- One point of contact across all workstreams
The project manager began by mapping each of the 50 patents to one of the three 5G domains. That decided which specialists belonged on which team, before any scheduling began. Starting from the patents, not from a list of names, is what kept each chart in the hands of someone who knew that part of the standard.
The experts were active practitioners in their domains. Several had taken part in 3rd Generation Partnership Project (3GPP) working groups.
The work followed the same five steps as every GHB Intellect litigation project: project intake, team building, expert analysis, quality assurance, and delivery with follow-up. Each technology area had a lead specialist and a backup, so one unavailable expert never stalled a chart.
QA managers reviewed each expert’s work iteratively to keep the charts consistent and complete, while the project manager tracked delivery, sent status updates, and handled the client’s change requests as they came in.
Each expert’s assessment of the accused products was independent of the client’s internal analysis, so the charts were built from what the products actually do, mapped to what the claims actually require.
Rolling delivery let counsel begin their own review while the final domain’s charts were still being drafted. A QA review caught and resolved technical issues at the chart level, before anything reached counsel for the first time.
Outcomes
- Deadline
- All 50 charts delivered within seven days
- Revisions required
- None to the technical substance after delivery
“The quality of service and the level of expertise has far exceeded our expectations.”
Related work
Claim chart development
Evidence-of-use charts at scale, staffed by domain.
Wireless and 5G
Experts matched to the 5G subspecialty your claims turn on.
Patent litigation support
Experts, claim charts, reverse engineering, and Patent Trial and Appeal Board (PTAB) support on one team, with one point of contact.
Tell us what you need to know
A senior person replies within one business day. All inquiries are confidential.